Timeline

Week
1 - 2

Site Layout & Excavation

• Verify site elevations
• Mark pool footprint
• Excavate pool and remove soil

Structural Steel & Bonding

• Install rebar for walls, steps,
benches, bond beam
• Set bonding grid

Week
3

Week
4

Plumbing & Electrical Rough-in

• Install suction/return plumbing
• Pressure test plumbing lines
• Run electrical conduit, grounding, and bonding
• Rough-in inspections

Structural Shell (Gunite / Shotcrete)

• Apply gunite/shotcrete to floor and walls
• Curing period begins

Week
5 - 6

Week
7

Tile, Coping & Deck Interfaces

• Install waterline tile
• Set coping
• Prepare deck interfaces with expansion joints

Equipment Set & Systems Installation

• Set pumps, filters, heaters, automation, sanitation
• Connect plumbing, electrical, and gas lines

Week
8

Week
9

Interior Finish Application

• Surface preparation
• Apply plaster, pebble, or quartz finish
• Begin controlled pool fill

Startup, Commissioning & Final Inspections

• Calibrate equipment and systems
• Balance water chemistry
• Final inspections
• Client orientation and turnover

Week
10