Timeline
Week
1 - 2
Site Layout & Excavation
• Verify site elevations
• Mark pool footprint
• Excavate pool and remove soil
Structural Steel & Bonding
• Install rebar for walls, steps,
benches, bond beam
• Set bonding grid
Week
3
Week
4
Plumbing & Electrical Rough-in
• Install suction/return plumbing
• Pressure test plumbing lines
• Run electrical conduit, grounding, and bonding
• Rough-in inspections
Structural Shell (Gunite / Shotcrete)
• Apply gunite/shotcrete to floor and walls
• Curing period begins
Week
5 - 6
Week
7
Tile, Coping & Deck Interfaces
• Install waterline tile
• Set coping
• Prepare deck interfaces with expansion joints
Equipment Set & Systems Installation
• Set pumps, filters, heaters, automation, sanitation
• Connect plumbing, electrical, and gas lines
Week
8
Week
9
Interior Finish Application
• Surface preparation
• Apply plaster, pebble, or quartz finish
• Begin controlled pool fill
Startup, Commissioning & Final Inspections
• Calibrate equipment and systems
• Balance water chemistry
• Final inspections
• Client orientation and turnover